Project Information
Supply and Installation of Structured Cabling System in Borouge II expansion, Survey, Cable pulling, Labeling, Termination and Testing of the Outside Plant Cabling System, Installation of Low voltage system including the following systems (PABX-Hot Line facilities, Public Address system, CCTV system, Master Clock system) Our job consists of:
- PABX-Hot Line Facilities – pulling of 750 meters of 20p telephone cable, installation of 11 Analogue telephones, laying of 9,600 meters telephone cable and power cable
- Public Address – installation of 17 central equipments, pulling of 5,080 meters cable for loudspeakers, laying of 34,671 meters of 2pair telephone cable, fixation of 488 loudspeakers
- CCTV – pulling of 8,800 meters of fiber optic cable and power cable, fixation, installation and testing of 9 CCTV cameras
- OPC – pulling of 43,868 meters of 24 core fiber optic cable with testing and pulling of 7,050 meters of 12 core fiber optic cable and drum testing
- Client : Thales International
- Date : 2009 – 2010
- Location : Ruwais
- Project Name : Borouge II Expansion
- Employees : 40